# PROCESS PURPOSE The purpose is to ensure that technical change requests are analyzed, tracked, and implemented. # PROCESS OUTCOMES
- O1 Technical change requests are analyzed, dependencies and relationships to other technical change requests are identified, and the impact is estimated
- O2 Implementation of technical change requests is confirmed
- O3 The status of all technical change requests is known, and technical change requests are tracked to closure
BP1
Analyze and assess technical change requests. (
O1 )

Linked Knowledge Nuggets:
arrow_forward "Change Requests and affected work items"
arrow_forward "Change Requests and affected work items"
BP2
Confirm the implementation of technical change requests. (
O2 )
BP3
Track technical change requests to closure. (
O3 )

Linked Knowledge Nuggets:
arrow_forward "ALM-based dashboard for monitoring Change Requests"
arrow_forward "ALM-based dashboard for monitoring Change Requests"
18-57
Change analysis criteria (
O1 )
Used by these processes:
- TCRM Technical Change Request Management
13-16
Change request (
O1, O2, O3 )
Used by these processes:
- TCRM Technical Change Request Management